Legislation Details

File #: 26-316    Version: 1 Name:
Type: Resolution Status: Passed
File created: 7/29/2026 In control: Public Works Committee
On agenda: Final action: 9/14/2026
Title: A RESOLUTION APPROVING AN INCREASE AND IMPROVEMENT OF FACILITIES OF THE ALBANY COUNTY WATER PURIFICATION DISTRICT IN THE COUNTY OF ALBANY, NEW YORK
Sponsors: Public Works Committee, Matthew J. Miller, Ellen Rosano
Attachments: 1. 2026.07.29_Gaudio_Cunningham_WPD Capital Project Approval, 2. RLA Form 7609, 3. WPD_2027-2031 Capital Plan, 4. Res 196 of 2026_Legislation Details (With Text), 5. 27-31 Capital Plan_Debt Service Summary, 6. WPD Public Hearing Notice_2026, 7. 26-316 PW 10 TMP-7609 - AlbanyC-49037- Water Purification District Resolution and Order AFTER Public Hearings
RESOLUTION NO. 316

A RESOLUTION APPROVING AN INCREASE AND IMPROVEMENT OF FACILITIES OF THE ALBANY COUNTY WATER PURIFICATION DISTRICT IN THE COUNTY OF ALBANY, NEW YORK

Introduced: 9/14/26
By Public Works Committee:

Recitals

WHEREAS, Pursuant to proceedings heretofore had and taken in accordance with the provisions of Article 5-A of the New York County Law, including approving orders of the State Comptroller, the Albany County Sewer District, has heretofore been established, and

WHEREAS, In October 2017, the name of the Albany County Sewer District was changed to the Albany County Water Purification District (the “District”); and

WHEREAS, The County of Albany (the “County”) has heretofore authorized the North and South Plant HVAC Upgrade Project (the “HVAC Upgrade Project”), which includes the study, design, and construction of improvements to existing HVAC systems at both the North and South Treatment Plants, expected to be completed in accordance with the engineering evaluation being prepared for the District by CHA Consulting Inc., Albany, New York, as part of the County’s 2025-2029 Capital Plan; and

WHEREAS, On September 8, 2025 the County Legislature adopted an amending bond resolution authorizing bonds in the principal amount of $1,500,000 for the HVAC Upgrade Project; and

WHEREAS, It has been determined that the estimated cost of said HVAC Upgrade Project has increased from $1,500,000 to $2,000,000 and that it is necessary and in the public interest to include such increase of $500,000 as part of the County’s 2027-2031 Capital Plan and to amend the bond resolution heretofore adopted for such project by a like amount; and

WHEREAS, Following a determination that certain upgrades to the District’s treatment facilities are necessary and in the public interest, the County has determined to undertake the design and installation of (1) an odor control system for the North Plant’s sludge holding tanks (the “Odor Control System Project”), expected to be compl...