REQUEST FOR LEGISLATIVE ACTION
Description (e.g., Contract Authorization for Information Services):
title
DGS Bond Resolution - Various Building Upgrades & Improvements B2301
body
Date: April 1, 2026
Department: General Services
Attending Meeting: Commissioner Latina
Submitted By: David M Latina
Title: Commissioner
Phone: 518-447-7210
Purpose of Request: Bond Approval Various Building Upgrades & Improvements B2301
CONTRACT TERMS/CONDITIONS:
Party Names and Addresses:
Enter text.
Term: (Start/end date or duration) Enter text.
Amount/Raise Schedule/Fee: $17,000,000.00
BUDGET INFORMATION:
Is there a Fiscal Impact: Yes ☒ No ☐
Anticipated in Budget: Yes ☒ No ☐
Spreadsheet attached: Yes ☐ No ☒
Source of Funding - (Percentages)
Federal: Enter text. County: 100%
State: Enter text. Local: Enter text.
County Budget Accounts:
Revenue Account and Line: Enter text.
Revenue Amount: Enter text.
Appropriation Account and Line: Enter text.
Appropriation Amount: Enter text.
ADDITIONAL INFORMATION:
Mandated Program/Service: Yes ☐ No ☒
If Mandated, Cite Authority: Enter text.
Request for Bids / Proposals:
Competitive Bidding Exempt: Yes ☐ No ☐
# of Response(s): Enter text.
# of MWBE: Enter text.
# of Veteran Business: Enter text.
Bond Resolution No.: Enter text.
Apprenticeship Program Yes ☐ No ☐
Previous requests for Identical or Similar Action:
Resolution/Law Number and Date: Enter text.
DESCRIPTION OF REQUEST: (state briefly why legislative action is requested)
The Department of General Services respectfully requests approval of a bond resolution authorizing
$17,000,000 for Various Building Upgrades & Improvements.
This project will address the long-term improvements to any / all County owned and operated facilities. Improvements will include, but not limited to, various upgrades such as mechanicals, HVAC, chillers, electrical, roofs, painting/carpeting, energy management systems, department moving & relocation costs, and engineering, structural, & property evaluations. NOTE: this project replaces several projects including, but not limited to, the County Office Building project, Facility Improvement Project, and the Office Modernization Project. These projects will generally have a useful life of 15 - 20 years.
These projects are included in the current Capital Plan - Various Building Upgrades & Improvements B2301.