REQUEST FOR LEGISLATIVE ACTION
Description (e.g., Contract Authorization for Information Services):
title
Authorization of a bond resolution in the amount of twenty million dollars for the Water Purification District’s Sludge Process Improvement Project that was approved under the 2022-2026 Capital Plan
body
Date: 1/31/2022
Submitted By: Angelo Gaudio
Department: Water Purification District
Title: Executive Director
Phone: 518-447-1624
Department Rep. Angelo Gaudio
Attending Meeting: Angelo Gaudio
Purpose of Request:
☐ Adopting of Local Law
☐ Amendment of Prior Legislation
☐ Approval/Adoption of Plan/Procedure
☒ Bond Approval
☐ Budget Amendment
☐ Contract Authorization
☐ Countywide Services
☐ Environmental Impact/SEQR
☐ Home Rule Request
☐ Property Conveyance
☐ Other: (state if not listed) Click or tap here to enter text.
CONCERNING BUDGET AMENDMENTS
Increase/decrease category (choose all that apply):
☐ Contractual
☐ Equipment
☐ Fringe
☐ Personnel
☐ Personnel Non-Individual
☐ Revenue
Increase Account/Line No.: Click or tap here to enter text.
Source of Funds: Click or tap here to enter text.
Title Change: Click or tap here to enter text.
CONCERNING CONTRACT AUTHORIZATIONS
Type of Contract:
☐ Change Order/Contract Amendment
☐ Purchase (Equipment/Supplies)
☐ Lease (Equipment/Supplies)
☐ Requirements
☐ Professional Services
☐ Education/Training
☐ Grant
Choose an item.
Submission Date Deadline Click or tap to enter a date.
☐ Settlement of a Claim
☐ Release of Liability
☐ Other: (state if not listed) Click or tap here to enter text.
Contract Terms/Conditions:
Party (Name/address):
Click or tap here to enter text.
Additional Parties (Names/addresses):
Click or tap here to enter text.
Amount/Raise Schedule/Fee: Click or tap here to enter text.
Scope of Services: Click or tap here to enter text.
Bond Res. No.: Click or tap here to enter text.
Date of Adoption: Click or tap here to enter text.
CONCERNING ALL REQUESTS
Mandated Program/Service: Yes ☐ No ☒
If Mandated Cite Authority: Click or tap here to enter text.
Is there a Fiscal Impact: Yes ☒ No ☐
Anticipated in Current Budget: Yes ☒ No ☐
County Budget Accounts:
Revenue Account and Line: Click or tap here to enter text.
Revenue Amount: Click or tap here to enter text.
Appropriation Account and Line: Click or tap here to enter text.
Appropriation Amount: Click or tap here to enter text.
Source of Funding - (Percentages)
Federal: Click or tap here to enter text.
State: Click or tap here to enter text.
County: 100
Local: Click or tap here to enter text.
Term
Term: (Start and end date) Click or tap here to enter text.
Length of Contract: Click or tap here to enter text.
Impact on Pending Litigation Yes ☐ No ☒
If yes, explain: Click or tap here to enter text.
Previous requests for Identical or Similar Action:
Resolution/Law Number: Click or tap here to enter text.
Date of Adoption: Click or tap here to enter text.
Justification: (state briefly why legislative action is requested)
Bond resolution is required to pursue funding and grant opportunities from Environmental Facilities Corporation (EFC) to demonstrate the County’s commitment and borrowing capacity for this project.
Project to include the engineering study, design and construction of improvements to the District’s existing sludge processing systems. The initial engineering study will evaluate improvements to the existing sludge processes required to comply with an active NYSDEC Order on Consent. Additionally the study will evaluate the option of consolidating both South Plant and North Plant sludge operations to the North Plant.