RESOLUTION NO. 17
AUTHORIZING AN AGREEMENT WITH PETER LUIZZI & BROTHERS CONTRACTING, INC. FOR THE CONSTRUCTION OF WATERVLIET SHAKER ROAD (CR157) PHASE III ROADWAY IMPROVEMENT PROJECT IN THE TOWN OF COLONIE
Introduced: 2/13/23
By Public Works Committee:
WHEREAS, By Resolution No. 277 for 2022, this Honorable Body authorized
an agreement with James H. Maloy, Inc. regarding the Watervliet Shaker Road (CR157) Phase III Roadway Improvement Tree Clearing and Grading Project in the Town of Colonie in an amount not to exceed $377,300 for a term commencing September 1, 2022 and ending November 30, 2022, and
WHEREAS, The Commissioner of the Department of Public Works has requested authorization to enter into an agreement with Peter Luizzi & Brothers Contracting, Inc. for the construction of Watervliet Shaker Road (CR157) Phase III Roadway Improvement Project in an amount not to exceed $7,338,483 for a term commencing April 1, 2023 and ending December 31, 2023, and
WHEREAS, The Department of Public Works, through the County Purchasing Agent, issued a request for bids and four bids were received, and
WHEREAS, The Department along with MJ Engineering and Land Surveying, P.C. reviewed said bids and has recommended awarding the contract to Peter Luizzi & Brothers Contracting, Inc., as the lowest responsible bidder, now, therefore, be it
RESOLVED, By the Albany County Legislature that the County Executive is authorized to enter into an agreement with Peter Luizzi & Brothers Contracting, Inc., Albany, NY 12205 for the construction of the Watervliet Shaker Road (CR157) Phase III Roadway Improvement Project in an amount not to exceed $7,338,483 for a term commencing April 1, 2023 and ending December 31, 2023, and, be it further
RESOLVED, That the County Attorney is authorized to approve said agreement as to form and content, and, be it further
RESOLVED, That the Clerk of the County Legislature is directed to forward certified copies of this resolution to the appropriate County Officials.