Contract Authorization with Gallo Construction Corporation for RFB 2025-173-GC MVP Arena Sound System Upgrade
body
Date: July 14, 2026
Department: General Services
Attending Meeting: Commissioner Latina
Submitted By: David M. Latina
Title: Commissioner
Phone: 518.447.7210
Purpose of Request: Contract Authorization General Construction Phase
CONTRACT TERMS/CONDITIONS:
Party Names and Addresses:
Gallo Construction Corp., 50 Lincoln Ave., Watervliet, NY 12189
Term: (Start/end date or duration) October 1, 2026- September 30, 2027
Amount/Raise Schedule/Fee: 448,000.00
BUDGET INFORMATION:
Is there a Fiscal Impact: YES
Anticipated in Budget: YES
Spreadsheet attached: NO
Source of Funding - (Percentages)
Federal: Enter text. County: 100%
State: Enter text. Local: Enter text.
County Budget Accounts:
Revenue Account and Line: Enter text.
Revenue Amount: Enter text.
Appropriation Account and Line: CAPIT
Appropriation Amount: 448,000.00
ADDITIONAL INFORMATION:
Mandated Program/Service: NO
If Mandated, Cite Authority: Enter text.
Request for Bids / Proposals:
Competitive Bidding Exempt: NO
# of Response(s): One (1)
# of MWBE: Enter text.
# of Veteran Business: Enter text.
Bond Resolution No.: 159 of 2024 & 236 of 2026
Apprenticeship Program YES
Previous requests for Identical or Similar Action:
Resolution/Law Number and Date: Enter text.
DESCRIPTION OF REQUEST: (state briefly why legislative action is requested)
Pursuant to RFB# 2025-173 RFB #2025-173-GC- MVP Arena Sound System Upgrade, General Services is requesting authorization of a contract with Gallo Construction Corp. with a not to exceed amount of $448,800.
This contract will provide general construction services for the project. The not to exceed total of this contract includes the base bid of $408,000 plus a 10% contingency of $40,800. Electrical and Mechanical Construction services for this project will be contracted separately.
This project is included in the 2026 MVP Arena Capital Plan C1801 and costs will be covered by Bonds HKV3 Res. No. 159 of 2024 and HKUW Res No 236 of 2026.
Gallo Construction Corp. has provided documentation of their participation in an apprentice
program.
The projected term of this contract is October 1, 2026, through September 30, 2027.
This proposed project meets the criteria established for SEQR Type II actions pursuant to 6 NYCRR 617.5(c) subdivision (1)(31). Accordingly, this action has been determined not to have a significant impact on the environment, and as such, no procedural compliance with SEQR beyond this determination is required at this time.