Attachments: 1. Cover Letter-Supplemental 6 MJ Eng., 2. 3204 RLA Form, 3. MJ Eng. Supplemental #6 Backup Material, 4. Resolution 82, 5. Resolution 86, 6. Resolution 322, 7. Resolution 455, 8. 22-187 PW 3 - TMP - 3204 - Authorizing_Supplemental_Agreement_MJ_Engineering_Rail_Trail_Bridge_New_Scotland_Rd_Bridge_NYS_85
RESOLUTION NO. 187

AUTHORIZING A SUPPLEMENTAL AGREEMENT WITH MJ ENGINEERING AND LAND SURVEYING, P.C. REGARDING EXPANDED DESIGN SERVICES FOR THE ALBANY COUNTY RAIL TRAIL OVER NEW SCOTLAND ROAD (NYS 85) BRIDGE REPLACEMENT PROJECT

Introduced: 6/13/22
By Public Works Committee:

WHEREAS, By Resolution No. 455 for 2018, this Honorable Body authorized an agreement with MJ Engineering and Land Surveying, P.C. regarding design and construction inspection services for the Albany County Rail Trail over New Scotland Road (NYS 85) Bridge Replacement Project in the amount of $95,500, and

WHEREAS, By Resolution No. 82 for 2019, this Honorable Body authorized amendments to Resolution No. 455 for 2018 to provide for emergency design and inspection services in the amount of $24,000, and to fund the State Environmental Quality Review (SEQR) Type I analysis for the project in the amount of $9,000 for a total amount of $128,500 rather than $95,500, and

WHEREAS, By Resolution No. 322 for 2019, this Honorable Body authorized a supplemental agreement with MJ Engineering and Land Surveying, P.C. regarding the expansion of design services for the Albany County Rail Trail over New Scotland Road (NYS 85) Bridge Replacement Project in the amount of $31,000 for a total contract amount of $159,500 rather than $128,500, and

WHEREAS, By Resolution No. 86 for 2020, this Honorable Body authorized a supplemental agreement with MJ Engineering and Land Surveying, P.C. in order to expand the scope of the project to include ten additional weeks of construction inspection services and capacity analysis for the temporary detour and intersection modifications for the Albany County Rail Trail over New Scotland Road (NYS 85) Bridge Replacement Project in the amount of $53,500 for a total contract amount of $213,000 rather than $159,500 for a term commencing April 1, 2020 and ending September 30, 2021, and

WHEREAS, The Commissioner of the Department of Public Works has reques...