Attachments: 1. Cover Letter, 2. 3926 RLA Form, 3. Concurrence, 4. Consultants Recommendation, 5. DPW Recommendation, 6. Eng. Recommendation, 7. Bid Tab Sheet, 8. Notice to Bidders, 9. RFB-2022-130 Addendum 1, 10. RFB-2022-130 Addendum 2, 11. RFB-2022-130 Addendum 3, 12. Resolution 470-BOND, 13. 23-078 PW 13 - TMP - 3926 - Authorizing_Agreement_William_J_Keller_&_Sons_Construction_CR352_Bridge_Replacement_Project

RESOLUTION NO. 78

 

AUTHORIZING AN AGREEMENT WITH WILLIAM J. KELLER & SONS CONSTRUCTION CORP. FOR THE CONSTRUCTION OF CR352 (FOX CREEK RD.) OVER FOX CREEK BRIDGE REPLACEMENT PROJECT IN THE TOWN OF RENSSELAERVILLE

 

Introduced:  3/13/23

                     By Public Works Committee:

 

                     WHEREAS, The Commissioner of the Department of Public Works has requested authorization to enter into an agreement with William J. Keller & Sons Construction Corp. for the construction of CR352 (Fox Creek Rd.) Over Fox Creek Bridge Replacement Project in the Town of Rensselaerville (Project) in an amount not to exceed $2,070,000 for a term commencing April 1, 2023 and ending December 31, 2023, and

 

WHEREAS, The Department of Public Works through the County Purchasing Agent issued a Request for Bids for the aforementioned Project, and four bids were received, and

 

                     WHEREAS, The Department and the Purchasing Agent reviewed said bids and recommended awarding the contract to William J. Keller & Sons Construction Corp. as the lowest responsible bidder, now, therefore, be it

 

RESOLVED, By the Albany County Legislature that the County Executive is authorized to enter into an agreement with William J. Keller & Sons Construction Corp., Castleton, NY 12033, for the construction of the Project in an amount not to exceed $2,070,000 for a term commencing April 1, 2023 and ending December 31, 2023, and, be it further

                     

RESOLVED, That the County Attorney is authorized to approve said agreement as to form and content, and, be it further

 

                     RESOLVED, That the Clerk of the County Legislature is directed to forward certified copies of this resolution to the appropriate County Officials.