Attachments: 1. Latina RLA cover letter 11 18 2022, 2. 3840 RLA Form, 3. Contract 1 GWC - Albany JDC RTA 11-17-22, signed, 4. Concur with Dept Recommendation-GC, 5. Bunkoff, 6. General Construction Tabulation, 7. Resolution 500 of 2021, 8. 22-519 PW 6 - TMP - 3840 - Authorizing_Agreement_Bunkoff_General_Contractors_Inc_CDYCI_Facility_Construction_Project

RESOLUTION NO. 519

 

AUTHORIZING AN AGREEMENT WITH BUNKOFF GENERAL CONTRACTORS, INC. REGARDING GENERAL WORK FOR THE CAPITAL DISTRICT JUVENILE SECURE DETENTION FACILITY CONSTRUCTION PROJECT

 

                     Introduced: 12/5/22

                     By Public Works Committee:

 

                     WHEREAS, The Commissioner of the Department of General Services has requested authorization to enter into an agreement with Bunkoff General Contractors, Inc. regarding general work for the Capital District Juvenile Secure Detention Facility Construction Project in an amount not to exceed $10,492,000 for a term commencing January 1, 2023 and ending December 31, 2025, and

 

                     WHEREAS, The Department, through the Purchasing Department, issued a Request for Bids for a General Work Contractor regarding the aforementioned project, and four bids were received, and

 

                     WHEREAS, After a review of the bids by the Department and Gilbane Building Company, the Department has recommended awarding the contract to Bunkoff General Contractors, Inc. as the lowest responsible bidder, now, therefore, be it

 

                     RESOLVED, By the Albany County Legislature that the County Executive is authorized to enter into an agreement with Bunkoff General Contractors, Inc., Latham, NY 12110 regarding general work for the Capital District Juvenile Secure Detention Facility Construction Project in an amount not to exceed $10,492,000 for a term commencing January 1, 2023 and ending December 31, 2025, and, be it further

 

RESOLVED, That the County Attorney is authorized to approve said agreement as to form and content, and, be it further

 

RESOLVED, That the Clerk of the County Legislature is directed to forward certified copies of this resolution to the appropriate County Officials.