RESOLUTION NO. 792
AUTHORIZING AN AGREEMENT WITH NATIONAL GRID ELECTRIC SERVICES, LLC REGARDING THE INSTALLATION OF A ROOFTOP SOLAR ARRAY AND ELECTRIC VEHICLE CHARGING STATIONS AT THE MVP ARENA PARKING GARAGE
Introduced: 12/2/24
By Audit and Finance Committee:
WHEREAS, The County Executive has requested authorization to enter into an agreement with National Grid Electric Services, LLC regarding the installation of a rooftop solar array and electric vehicle charging stations at the MVP Arena Parking Garage in an amount not to exceed of $7,921,747 for a term commencing January 1, 2025 and ending December 31, 2025, and
WHEREAS, The solar array is projected to generate 1.15 gigawatt hours per year for an estimated savings to the County of $154,500, and
WHEREAS, National Grid Electric Services, LLC is contracted through the Utility Energy Services Contract program, now, therefore, be it
RESOLVED, By the Albany County Legislature that the County Executive is authorized to enter into an agreement with National Grid Electric Services, LLC, Waltham, MA 02451 regarding the installation of a rooftop solar array and electric vehicle charging stations at the MVP Arena Parking Garage in an amount not to exceed $7,921,747 for a term commencing January 1, 2025 and ending December 31, 2025, and, be it further
RESOLVED, That the County Attorney is authorized to approve said agreement as to form and content, and, be it further
RESOLVED, That the Clerk of the County Legislature is directed to forward certified copies of this resolution to the appropriate County Officials.